Most of the planned 14 Supercharging terminals have been installed.
Please scroll down to the bottom of the article for current updates.
A number of our club members have discovered the “Coming Soon” Union Park Supercharger Station under construction at the at Waterford Lakes Town Center near the Regal Cinemas in the parking lot of The Social House restaurant (435 N Alafaya Trail, Orlando, FL 32828).
Here is a vicinity map. (For a full sized images right click on the images and open them in a new tab.)

Here are some photos of the installation.



From photos taken it appears that there will be 14 – 120 kW charging terminals. As of December 2, 2018, most of the charging terminals were installed, 7 Supercharger Cabinets (white cabinets) and the high voltage switchgear (grey cabinets) have also been installed.
The utility has yet to set the concrete pad, power transformer and install the meter.
The annual carnival is being set up in the same parking lot so the Supercharger Station is currently totally blocked off. It is therefore unlikely that any additional utility work will proceed for a while.
Update as of January 20, 2019:
It looks like Tesla's contractor has completed its work and the local utility has set the power transformer. The only thing that appears to be required is the installation of the meter in the meter cabinet.


Update as of February 14, 2019.
The Union Park Supercharger Station is now operational.